The steel roofing in place and some of the rough in of the wiring. The rough in of the wiring will be completed by Friday.
The soffit is here and will be installed after preliminary work is completed.
The siding was delivered today and installation will be started as soon as the doors and windows are installed.
The cabinets are on order and scheduled to be here in about 6 weeks.
The weather continues to be a thorn in the side.